This is the proposed three year plan for remodeling the house on Oakshade Road. We will update this as additional progress is made. 
Planned activities for the first year 09-01-18 through 09-01-19
| Activity | Progress |
| Property Survey by Guzzi Engineering | Completed |
| Replace rotted sill plate rear and side | Not Completed |
| Replace side porch | Not Completed |
| New well w/pump and piping into basement | Not Completed |
| New septic system with piping into basement | Not Completed |
| Natural gas line installed | Not Completed |
| New heater installed in basement | Not Completed |
Planned activities for the second year 09-01-19 through 09-01-20
| Activity | Progress |
| Gut the interior ceiling and walls | In-progress |
| Install new wiring and fixtures | Not completed |
| Install new insulation, sheet-rock ceiling and walls | Not completed |
| Refinish the kitchen area | Not completed |
| Install stairs to basement | Not completed |
| Install handicap toilet on first floor | Not completed |
| Connect septic and water to fixtures | Not completed |
| Install fire and burglar alarm system | Not completed |
Planned activities for the third year 09-01-20 through 09-001-21
| Activity | Progress |
| Install new roof | Not completed |
| Install new siding | Not completed |